7th Avenue Construction Update

Update

City of West Bend recently issued the following announcement.

On Tuesday, October 5, 2021, paving will commence on 7th Avenue and the city anticipates reopening the road to traffic on November 8, 2021.

The contractor will start paving from Washington Street south toward Walnut Street. Concrete trucks will primarily enter the project area from Walnut Street and exit onto Washington Street.

Below is the projected project timeline:

  • October 5-11 - Paving of the southbound lanes
  • October 5 - Concrete sawing in afternoon and evening
  • October 12-18 - Paving of the northbound lanes
  • October 12-13 - Concrete sawing in afternoon and evening
  • October 18-24 - Curb, gutter, and sidewalks
  • October 25-31 - Street intersections
  • November 1-7 - Restoration, pavement markings, signage
  • November 8 - Road opens to traffic
Concrete sawing may be disruptive. Our team will work to keep noise to a minimum. Thank you for your patience as we work to finish this project.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS