Roadwork Project – Main St. West. to be held Aug 2

Road

Issued the following announcement.

Roadwork Project – Main St. West.

DATE

Jul 16 2021 - Aug 09 2021Ongoing...

VILLAGE OF NEWBURG

MAIN STREET WEST – PULVERIZE & OVERLAY PROJECT

To keep residents aware of construction needs and work in the Main Street West

Pulverize and Overlay Project area, we would like to share an update prior to

construction to the affected residents. Stantec Project Engineer Christian Moring

is available to answer any questions regarding the project. You may contact him

at 262-665-3012 or christian.moring@stantec.com.

The Village understands that a project like this causes disruptions to everyday

life. We appreciate your patience would like to remind you to drive slowly

through the project area in order to keep yourself and workers safe.

PROJECT TIMELINE

July 16, 2021: Traffic control setup (see attached detour route).

 Week of July 19: Pulverizing and grading roadway.

 Week of July 26: Excavation and application of first layer of asphalt.

 Week of August 2: Application of final layer of asphalt.

 Week of August 9: Pavement markings, restoration efforts, and

construction move out.

ADDITIONAL NOTES

 Residents and businesses along the project route will maintain access

to their driveways throughout the duration of the project.

Mail will not be interrupted during construction.

 Main Street West will be closed to through traffic and a detour route will be available.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate